Delhi Metro News: Major milestone! DMRC achieves breakthrough – What commuters should know

This new tunnel stretch is a continuation of the earlier Magenta line tunnel that was already constructed for the presently operational Botanical Garden Janakpuri West corridor.

The Delhi Metro Rail Corporation on Saturday said it has achieved a major milestone with the completion of tunnelling work between Krishna Park Extension and Keshopur on its Janakpuri West-RK Ashram Marg corridor here.

As part of phase 4 construction, a 73-metre-long Tunnel Boring Machine (TBM) broke through at Krishna Park Extension after boring a 1.4-kilometre long tunnel in the presence of the secretary, Ministry of Housing and Urban Affairs Manoj Joshi, DMRC Managing Director Vikas Kumar and other senior officials.
Two parallel circular tunnels for up and down movement have been constructed on this stretch, which is part of a 2.2-kilometre-long underground section from Janakpuri West to Keshopur. The work on the other parallel tunnel on this section was completed in December last year, the DMRC said in a statement.

The completion of this stretch is a significant achievement for DMRC since this work faced repeated constraints due to the Covid pandemic.

“The workforce was retained following all the guidelines, and the work schedule was planned accordingly. On this underground stretch, apart from the twin tunnels, the ramp and the entry/ exit have been completed while about 70 per cent of the Krishna Park Extension station has also been completed.

“Civil work of this particular underground section will be completed by early next year though the entire Janakpuri West  RK Ashram Marg corridor will be ready by September, 2025,” the statement read.

This new tunnel stretch is a continuation of the earlier Magenta line tunnel that was already constructed for the presently operational Botanical Garden Janakpuri West corridor.

The tunnel has been constructed approximately at a depth of 14 to 16 metres. About 2,000 rings have been installed in the tunnel. It has an inner diameter of 5.8 metres. The alignment of the tunnel runs along the Outer ring road and below multi-storied built-up structures, it said.

The tunnelling work involved many challenges like shifting of sewer lines at a depth of eight metres using the micro tunneling method. In addition, due to heavy traffic on the Outer Ring Road, a subway was constructed using the box-pushing method without disturbing the traffic flow, it said.

The tunnel has been built with the proven technology of EPBM (Earth pressure balancing method) with concrete lining made up of precast tunnel rings. The tunnel rings have been cast at the fully mechanized casting yard setup at Mundka, it said. These concrete segments were cured with a steam curing system to achieve early strength, it added.

As part of the Phase 4 work approved so far, 28.76 kilometres of underground lines will be constructed. The Janakpuri West RK Ashram Marg corridor will have underground sections of 9.41 kilometres in total.

A TBM is a machine used to excavate tunnels with a circular cross-section through a variety of soil and rock strata. They can be designed to bore through anything from hard rock to sand. TBMs have revolutionized the way tunnelling work is done worldwide as tunnels can now be bored without disturbing the buildings and other structures on the surface.